Officers already decide almost everything. In April to June 2026 they made 72,100 of the 74,500 planning decisions by district-level planning authorities in England, or 97%. What the national scheme of delegation changes is the remainder. The government's impact assessment estimates that committees decide nearly 40% of major residential applications, so the remainder includes many of the large housing schemes.
From 31 October the rules for that share are set by S.I. 2026/854, not by each council's constitution. The scheme does not apply to national park authorities, the Broads Authority, development corporations or Homes England (guidance, paragraph 2). An application in a national park still follows the park authority's own scheme of delegation.
The two lists
Schedule 1, officers only. Householder, minor commercial and minor residential applications, permission in principle, discharge of conditions, prior approvals, certificates of lawfulness, non-material amendments, and reserved matters on any outline below the large-scheme threshold. A committee may not decide these, with exceptions. An application connected to listed building consent, or made under section 73A, moves to Schedule 2 (guidance, paragraph 19). An own-interest application can be referred by the two nominees (regulation 6): one made by or for the council or one of its members or officers, or one in which the nominees think any of them has an interest. The guidance warns that a committee decision on a Schedule 1 application after 31 October "may be subject to judicial review by anyone aggrieved by the decision".
Schedule 2, officers unless referred. Most other applications, including majors, listed building consent, advertisement and tree preservation order consents, and reserved matters on outlines for 500 or more homes or 50,000 square metres. Anything in neither schedule is left to the council's constitution (guidance, paragraph 8).
Three thresholds that catch people out
Site area. Minor residential mainly means 1 to 9 homes on a site smaller than 0.5 hectares. Nine homes on 0.6 hectares is a Schedule 2 case.
Retrospective applications. Anything under section 73A is Schedule 2, however small, including a householder extension already built.
Section 73. A variation follows the schedule of the original permission, so an amendment to a major stays in Schedule 2.
The gateway
A Schedule 2 application reaches committee only if the nominated member and the nominated officer agree it raises "one or more issues of economic, social or environmental significance to the local area" or "one or more significant planning matters having regard to the development plan and any other material considerations" (regulation 5(3)). The guidance says the nominees should be the planning committee chair and the chief planning officer, and that referral should be "only exceptionally". If they disagree, officers decide.
Two passages in the guidance help an applicant (paragraph 24). A scheme that "broadly complies with a detailed site allocation and other relevant policies" is unlikely to raise a significant planning matter, though the guidance adds that one may arise "if new material considerations are raised by the application". Nor, usually, is a concern a statutory consultee raised that has since been resolved to the consultee's satisfaction, unless the nominated officer has compelling reasons to think otherwise. An application on an allocated site, with consultee concerns closed out before the gateway meets, can point to both passages. The two nominees still decide, and size still counts: the guidance's first example of a case that might be referred is an outline application for "a large multi-phase residential development allocated in the local plan".
Councillor call-in and objection-count triggers "will not be possible" (paragraph 9). Some councils, Cotswold amongst them, are replacing call-in with a written request from a member, which the two nominees then consider. The guidance says requests and outcomes should be recorded, reported to committee and published (paragraph 34), so applicants should be able to see why a referral was made.
Why the government wants it
The impact assessment cites Lichfields' analysis of appeals for schemes of 50 or more homes in England from January 2021 to August 2024. In that sample, 33% followed a committee refusal against officer advice, and 79% of those were allowed. That is an average across committees that behave differently. It puts the delay an appeal adds at about 200 days. The Planning Advisory Service found committees typically meet monthly and take two to four applications each time.
The Local Government Association supported faster decisions but warned of the "potential erosion of local democracy and the limited flexibility created by a highly standardised national scheme of delegation". Committees are capped at 13 members, and the regulations must be reviewed by 31 October 2028.
What to do with a live application
The regulations contain no transitional provision for applications already in the system, and the impact assessment says "There will be no transitional arrangements". Check which schedule an application falls in under the new rules, whenever it was submitted. If it is Schedule 2, assume a member request is possible within the council's window, and put the scheme's compliance with the allocation and its consultee position on the file early, in terms the gateway can use.
Sources
- The Town and Country Planning (Discharge of Local Planning Authority Functions) (England) Regulations 2026, S.I. 2026/854, made 15 July 2026, in force 31 October 2026, and its explanatory memorandum.
- Ministry of Housing, Communities and Local Government, Planning Committees and the National Scheme of Delegation of Planning Functions: Guidance for local planning authorities in England, 1 June 2026.
- Ministry of Housing, Communities and Local Government, Planning committee modernisation: impact assessment, 4 June 2026, including figures from Lichfields and the Planning Advisory Service.
- Ministry of Housing, Communities and Local Government, Planning applications in England: April to June 2026, 24 September 2026.
- Local Government Association, response to the consultation on the draft regulations, as reported by Local Government Lawyer, April 2026.